Refurbishment of Main Train Shed Roof for Network Rail
Robinson Kenning & Gallagher produced a Listed Building Application with WYG on behalf of Network Rail for works relating to the refurbishment of the main train shed at Kings Cross Station, London. The Client brief required a detailed survey of the main train shed roof (primarily two large barrel vaults separated by a brick central spine wall) including, detailed structural assessments and inspection, and a condition survey of both the interior and exterior fabric to the roof coverings.
Over a ten-month timescale, regular meetings were held with Camden Conservation Planners and English Heritage representatives, in order to relate the results of the structural investigations and to develop an acceptable proposed design for the refurbishment of the main train shed. A presentation was made to Camden Conservation Planners and English Heritage identifying alternative design options for addressing structural concerns. Amongst other criteria, the presentation was based on wind tunnel test results, impact of snow (and snow drifts) calculations and recommendations for improving performance of the bow string purlins.
OTHER TRANSPORT CASE STUDIES:
Initial concept design Grip Stage 5 working drawings of a New Major Interchange Station at Dartford, incorporating new retail, passenger and station staff administration facilities. In association with the scheme the existing car parking was also developed to increase the number of parking spaces and improve Disabled parking and its proximity to the new station.
Earlsfield Station is the busiest small station in London, experiencing huge volumes of passenger flow during peak hours.
Robinson Kenning & Gallagher prepared scheme proposals, working drawings, and invitation to tender documents for the development of this South West Trains flagship station at Basingstoke. RKG were also employed to act as Project Managers and Supervisors under the NEC 3 contract.
Robinson Kenning & Gallagher prepared listed building and permitted development proposals, working drawings, and invitation to tender documents for the development of this South West Trains new Cycle Hubs at 8no Stations.
Robinson Kenning & Gallagher were employed from Grip stage 2 ñ 8 working closely with Balfour Beatty Rail, Network Rail and the End User.
This original entrance to the station had become congested and the pedestrian flow of passenger through the subway was being restricted by the existing gateline and limited circulation space.
Morgan Sindall were appointed Principal Contractor for the proposed Access for All works at the station. Robinson Kenning & Gallagher were appointed as Architects for the scheme.
RKG were employed to produce the architectural detailed design and Form 003 submission along with the overall coordination of Structural, Mechanical & Electrical †and Signage for the new public waiting room.
Morgan Sindall were appointed Principal Contractor for the proposed Access for All works at the stations. Robinson Kenning & Gallagher were appointed as Architects for the scheme.
Robinson Kenning & Gallagher were appointed as Architects for the scheme to provide detailed design for the new lifts and walkways.
Robinson Kenning & Gallagher produced a Listed Building Application with WYG on behalf of our clients Network Rail. Network Rail is proposing to refurbish and upgrade Kings Cross Station. This Application related to the proposed renewals work and specifically to the Main Train Shed which comprises of two separate barrels roof separated by a central spine wall.
Robinson Kenning & Gallagher acted as Heritage consultants for the mains contractor for the re-roofing of the Eastern Kent side Concourse of London Victoria Station.
Robinson Kenning & Gallagher were appointed as Architects for the scheme to provide detailed design for the new lifts and walkways.