Norwich Station, Trainshed Roof

Feasibility Options for refurbishment of Existing Train Shed and Side Porte-Cochere

The existing Norwich railway station trainshed and side porte-cochere roofs are in poor condition. RKG acting as Lead consultants and Architects undertook feasibility options report  for a GRIP (Governance for Railway Investment Projects) Stage 3 ‘Option Selection’ to evaluate the potential of introducing replacement material and finishes to the existing trainshed roof and side porte-cochere roof.

The objectives of the report in conjunction with the brief are as follows:

•Assess options for the proposed replacement of materials and finishes to the main trainshed roofs, to the main trainshed upper gable end, and the side porte-cochere roof.

•Assess the colour scheme and redecoration of the existing trainshed and side porte-cochere structures.

•Assess gutter repair and lining options

•Assess scaffolding - multi purpose protection

•Assess fall protection systems / safe access systems

View fullsize 01 Image.jpg
View fullsize 02 Image.JPG
View fullsize 03 Image.jpg
View fullsize 04 Image.jpg
View fullsize 05 Image.JPG
View fullsize 06 Image.jpg

OTHER LIVE PROJECT CASE STUDIES:

Featured
Arklow Road, Lewisham
Arklow Road, Lewisham
St Erth, Cornwall
St Erth, Cornwall
Bury St. Edmunds Station (Cycle Hub), Suffolk
Bury St. Edmunds Station (Cycle Hub), Suffolk
North Shields, Newcastle
North Shields, Newcastle
Bristol Temple Meads, Bristol
Bristol Temple Meads, Bristol
Cambridge CyclePoint, Cambridge
Cambridge CyclePoint, Cambridge
categories: Transport
Monday 07.29.24
Posted by Kevin Stocker
 

Stoke MDU, Stoke

Stoke MDU, Stoke

The Stoke MDU Project for Network Rail on behalf of Cleshar Contracts Services Ltd. and Crouch Waterfall, consisted of two new buildings, a 450m² warehouse with associated offices and WC facilities and a single storey office building. The office building includes office space, meeting rooms, changing facilities and mess area/seminar room. The project also included a complete redesign of the site and therefore storage areas and parking facilities. The office building was designed using SIP’s (Structural Insulated Panel System) and was completed on site in 2022.

View fullsize 01 Stoke.jpg
View fullsize 02 Stoke.JPG
View fullsize 03 Stoke.jpg
View fullsize 04A image.jpg
View fullsize 04 Stoke.jpg
View fullsize 04a Stoke 5a.jpg
View fullsize 05 Stoke.jpg
View fullsize 05a Stoke.jpg
View fullsize 06 Stoke.jpg
View fullsize 07 Stoke.jpg
View fullsize 07a Stoke.jpg
View fullsize 08 Stoke.jpg

OTHER LIVE PROJECT CASE STUDIES:

Featured
Arklow Road, Lewisham
Arklow Road, Lewisham
St Erth, Cornwall
St Erth, Cornwall
Bury St. Edmunds Station (Cycle Hub), Suffolk
Bury St. Edmunds Station (Cycle Hub), Suffolk
North Shields, Newcastle
North Shields, Newcastle
Bristol Temple Meads, Bristol
Bristol Temple Meads, Bristol
Cambridge CyclePoint, Cambridge
Cambridge CyclePoint, Cambridge
categories: Transport
Tuesday 01.16.24
Posted by Kevin Stocker
 

Bury St. Edmunds Station, Suffolk

Station Entrance Works for Greater Anglia

Robinson Kenning & Gallagher are delighted to announce we have been employed by Greater Anglia to produce a Detail Design Architectural Drawings and Heritage Statement for the reconfiguration of the existing booking hall and new northern entrance area of Bury St. Edmunds Station, Suffolk.

The works involve co-ordination with other design disciplines to produce a design that future proofs the station whilst protecting the new works from the inherent challenges of working on a listed building where the accommodation is mostly located beneath overhead tracks.

View fullsize 01 image.jpg
View fullsize 02 image.jpg
View fullsize 03 image.jpg
View fullsize 04 image.jpg
View fullsize 05 image.jpg
View fullsize 06 image.jpg
View fullsize 07 image.jpg
View fullsize 08 image.jpg
View fullsize 09 image.jpg
View fullsize 10 image.jpg
View fullsize 11 image.jpg

OTHER LIVE PROJECT CASE STUDIES:

Featured
Arklow Road, Lewisham
Arklow Road, Lewisham
St Erth, Cornwall
St Erth, Cornwall
Bury St. Edmunds Station (Cycle Hub), Suffolk
Bury St. Edmunds Station (Cycle Hub), Suffolk
North Shields, Newcastle
North Shields, Newcastle
Bristol Temple Meads, Bristol
Bristol Temple Meads, Bristol
Cambridge CyclePoint, Cambridge
Cambridge CyclePoint, Cambridge
categories: Transport
Tuesday 01.16.24
Posted by Kevin Stocker
 

Amersham Station, London

New Step-Free Access for London Underground

Robinson Kenning & Gallagher have been appointed as Sub-Consultants to provide architectural design elements for this new ‘Step-Free Access’ scheme. Working with the Lead Consultant (Ramboll) as part of Taylor Woodrow/BAM Nuttall design team a new overbridge with two lift towers and staff-access staircase has been designed.

The new overbridge and lift towers are to be sighted at the west end of the Station and will form a new freestanding structure. Access to the new overbridge will be via the new lift towers which will provide access from Platform 3 (main Station entrance side) to the island platform (platforms 1 and 2). A staff access staircase is also to be provided for maintenance and emergency use only.

The design and location of the new lift towers and overbridge has been carefully considered to achieve not only the best operational location but also the visual impact on the existing single storey station building.

Taylor Woodrow/BAM Nuttall are the main contractor delivering these works for London Underground. Website images of construction provided curtesy of Taylor Woodrow/BAM Nuttall.

View fullsize 13-01-2020 (70).jpg
View fullsize 13-01-2020 (3).jpg
View fullsize 13-01-2020 (18).jpg
View fullsize 13-01-2020 (5).jpg
View fullsize 13-01-2020 (50).jpg
View fullsize 13-01-2020 (54).jpg

OTHER LIVE PROJECT CASE STUDIES:

Featured
Arklow Road, Lewisham
Arklow Road, Lewisham
St Erth, Cornwall
St Erth, Cornwall
Bury St. Edmunds Station (Cycle Hub), Suffolk
Bury St. Edmunds Station (Cycle Hub), Suffolk
North Shields, Newcastle
North Shields, Newcastle
Bristol Temple Meads, Bristol
Bristol Temple Meads, Bristol
Cambridge CyclePoint, Cambridge
Cambridge CyclePoint, Cambridge
categories: Transport, Access for All
Tuesday 01.16.24
Posted by Kevin Stocker
 

Harrow-on-the-Hill, London

New Step-Free Access for London Underground

Robinson Kenning & Gallagher have been appointed as Sub-Consultants to provide architectural design elements for this new ‘Step-Free Access’ scheme. Working with the Lead Consultant Ramboll as part of Taylor Woodrow/BAM Nuttall design team to design and detail a new link bridge with three lift towers and direct access to the elevated booking hall.

The new link bridge and lift towers provide access to platforms 1-6. Access to the new link bridge is via a new formed opening in the booking hall.

Access from the northern end of the station has also been addressed by a new lift providing access from street level to Booking Hall level. A new dedicated passenger route was created to link this lift to the booking hall.

The design and location of the new lift towers and link bridge has been carefully considered to achieve not only the best operational location.

Taylor Woodrow/BAM Nuttall are the main contractor delivering these works for London Underground. Website images of construction provided curtesy of Taylor Woodrow/BAM Nuttall.

View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5566.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5646.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5647.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5390.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5402.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5525.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5657.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5670.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5708.JPG
View fullsize 080222 BAM Nuttall Harrow on the Hill jz543A5757.JPG

OTHER LIVE PROJECT CASE STUDIES:

Featured
Arklow Road, Lewisham
Arklow Road, Lewisham
St Erth, Cornwall
St Erth, Cornwall
Bury St. Edmunds Station (Cycle Hub), Suffolk
Bury St. Edmunds Station (Cycle Hub), Suffolk
North Shields, Newcastle
North Shields, Newcastle
Bristol Temple Meads, Bristol
Bristol Temple Meads, Bristol
Cambridge CyclePoint, Cambridge
Cambridge CyclePoint, Cambridge
categories: Transport, Access for All
Monday 01.15.24
Posted by Kevin Stocker
 

Dartford Station, Kent

Initial concept design Grip Stage 5 working drawings of a New Major Interchange Station at Dartford, incorporating new retail, passenger and station staff administration facilities. In association with the scheme the existing car parking was also developed to increase the number of parking spaces and improve Disabled parking and its proximity to the new station.

Read more

categories: Transport, Access for All
Thursday 08.15.19
Posted by 3B Digital
 

Earlsfield Station, London

Earlsfield Station is the busiest small station in London, experiencing huge volumes of passenger flow during peak hours.

Read more

categories: Transport, Access for All
Wednesday 08.14.19
Posted by 3B Digital
 

Basingstoke Station, Hampshire

Robinson Kenning & Gallagher prepared scheme proposals, working drawings, and invitation to tender documents for the development of this South West Trains flagship station at Basingstoke. RKG were also employed to act as Project Managers and Supervisors under the NEC 3 contract.

Read more

categories: Transport
Tuesday 08.13.19
Posted by 3B Digital
 

Euston Station, London

View fullsize 01 Image.jpg
View fullsize 02 Image.jpg
View fullsize 03 Image.jpg
View fullsize 04 Image.jpg
View fullsize 05 Image.jpg
View fullsize 06 Image.jpg
View fullsize 07 Image.jpg
View fullsize 08 Image.jpg
View fullsize 10 Image.jpg
View fullsize 09 Image.jpg

Complete Refurbishment of Concourse Retail for Network Rail

Robinson Kenning & Gallagher were appointed by Balfour Beatty to provide Grip 4 to 8, multi-discipline design and technical site support for the complete refurbishment of the Station retail facilities. Included in the works was the provision of a new 1,200m² mezzanine floor to facilitate a selection of new dining outlets and customer seating areas. 

Detailed design development included: consideration for shopper and passenger movement between the new mezzanine and existing Station facilities, the declutter of the Station concourse and the conversion of the existing piazza and food court areas. 

Sited over the main station concourse and busy LUL escalators, working alongside the live Station environment, the passenger safety and continuity of Station operations was paramount. In total fifteen new retail units were provided as part of the refurbishment scheme.

Project Value: £9m


OTHER ACCESS FOR ALL CASE STUDIES:

Featured
Norwich Station, Trainshed Roof
Norwich Station, Trainshed Roof
Stoke MDU, Stoke
Stoke MDU, Stoke
Bury St. Edmunds Station, Suffolk
Bury St. Edmunds Station, Suffolk
Amersham Station, London
Amersham Station, London
Harrow-on-the-Hill, London
Harrow-on-the-Hill, London
Dartford Station, Kent
Dartford Station, Kent
Earlsfield Station, London
Earlsfield Station, London
Basingstoke Station, Hampshire
Basingstoke Station, Hampshire
Euston Station, London
Euston Station, London
Cycle Hubs, South West England
Cycle Hubs, South West England
London Bridge: Maintenance Facility, London
London Bridge: Maintenance Facility, London
Clapham Junction Station: Brighton Yard, London
Clapham Junction Station: Brighton Yard, London
Southampton Station, Hampshire
Southampton Station, Hampshire
Kensal Rise and South Tottenham Overground Stations, London
Kensal Rise and South Tottenham Overground Stations, London
Paddington Station: Waiting Room, London
Paddington Station: Waiting Room, London
Clapham Junction: St John's Hill Entrance, London
Clapham Junction: St John's Hill Entrance, London
Charing Cross Station, London
Charing Cross Station, London
Clapham Junction: Platform 9/10, London
Clapham Junction: Platform 9/10, London
Worcester Park and New Malden Stations, South London
Worcester Park and New Malden Stations, South London
Ilford Station: Public Toilets & Waiting Room, London
Ilford Station: Public Toilets & Waiting Room, London
Kings Cross Station: Roof, London
Kings Cross Station: Roof, London
Victoria Station: Eastern Barrel Roofs, London
Victoria Station: Eastern Barrel Roofs, London
Blackhorse Road Station, London
Blackhorse Road Station, London
categories: Transport, Access for All
Monday 08.12.19
Posted by Kevin Stocker
 

Cycle Hubs, South West England

Robinson Kenning & Gallagher prepared listed building and permitted development proposals, working drawings, and invitation to tender documents for the development of this South West Trains new Cycle Hubs at 8no Stations.

Read more

categories: Transport
Sunday 08.11.19
Posted by 3B Digital
 

London Bridge: Maintenance Facility, London

Robinson Kenning & Gallagher were employed from Grip stage 2 ñ 8 working closely with Balfour Beatty Rail, Network Rail and the End User.

Read more

categories: Transport
Saturday 08.10.19
Posted by 3B Digital
 

Clapham Junction Station: Brighton Yard, London

This original entrance to the station had become congested and the pedestrian flow of passenger through the subway was being restricted by the existing gateline and limited circulation space.

Read more

categories: Transport, Access for All
Friday 08.09.19
Posted by 3B Digital
 

Southampton Station, Hampshire

Entrance Improvements, New Concourse and Upgraded Passenger Facilities and Forecourt

A National Station Improvement Project (NSIP) for Network Rail on behalf of South West Trains (SSWT). Robinson Kenning & Gallagher designed a new fully DDA compliant Station entrance, enlarged booking hall and new ticket office counters. Other improvements included a new passenger lounge and toilet areas, dedicated customer information counter and improved circulation arrangements with the retail unit. New facilities were also designed for the TOC (Train Operating Company) train crew.

RKG were appointed to provide Grip 3 and 4 Design Development. Feasibility options improved the poor access arrangements around the Station entrance and enhanced both passenger and retail amenities. RKG completed Grip 5 Design and site support works for Osborne based on a tight construction programme. The new Station entrance works (the 250th NSIP Project) were in keeping with the Art Deco styling of the station and were well received by the Client. The Station was re-opened by the Secretary of State for Transport.

View fullsize 02 Image.jpg
View fullsize 01 Image.jpg
View fullsize 03 Image.jpg
View fullsize 04 Image.jpg
View fullsize 05 Image.jpg
View fullsize 06 Image.jpg
View fullsize 07 Image.jpg
View fullsize 08 Image.jpg
View fullsize 09 Image.jpg
View fullsize 10 Image.jpg

OTHER ACCESS FOR ALL CASE STUDIES:

Featured
Norwich Station, Trainshed Roof
Norwich Station, Trainshed Roof
Stoke MDU, Stoke
Stoke MDU, Stoke
Bury St. Edmunds Station, Suffolk
Bury St. Edmunds Station, Suffolk
Amersham Station, London
Amersham Station, London
Harrow-on-the-Hill, London
Harrow-on-the-Hill, London
Dartford Station, Kent
Dartford Station, Kent
Earlsfield Station, London
Earlsfield Station, London
Basingstoke Station, Hampshire
Basingstoke Station, Hampshire
Euston Station, London
Euston Station, London
Cycle Hubs, South West England
Cycle Hubs, South West England
London Bridge: Maintenance Facility, London
London Bridge: Maintenance Facility, London
Clapham Junction Station: Brighton Yard, London
Clapham Junction Station: Brighton Yard, London
Southampton Station, Hampshire
Southampton Station, Hampshire
Kensal Rise and South Tottenham Overground Stations, London
Kensal Rise and South Tottenham Overground Stations, London
Paddington Station: Waiting Room, London
Paddington Station: Waiting Room, London
Clapham Junction: St John's Hill Entrance, London
Clapham Junction: St John's Hill Entrance, London
Charing Cross Station, London
Charing Cross Station, London
Clapham Junction: Platform 9/10, London
Clapham Junction: Platform 9/10, London
Worcester Park and New Malden Stations, South London
Worcester Park and New Malden Stations, South London
Ilford Station: Public Toilets & Waiting Room, London
Ilford Station: Public Toilets & Waiting Room, London
Kings Cross Station: Roof, London
Kings Cross Station: Roof, London
Victoria Station: Eastern Barrel Roofs, London
Victoria Station: Eastern Barrel Roofs, London
Blackhorse Road Station, London
Blackhorse Road Station, London
categories: Transport, Access for All
Thursday 08.08.19
Posted by Kevin Stocker
 

Kensal Rise and South Tottenham Overground Stations, London

Morgan Sindall were appointed Principal Contractor for the proposed Access for All works at the station. Robinson Kenning & Gallagher were appointed as Architects for the scheme.

Read more

categories: Transport, Access for All
Wednesday 08.07.19
Posted by 3B Digital
 

Paddington Station: Waiting Room, London

RKG were employed to produce the architectural detailed design and Form 003 submission along with the overall coordination of Structural, Mechanical & Electrical †and Signage for the new public waiting room.

Read more

categories: Transport
Tuesday 08.06.19
Posted by 3B Digital
 

Clapham Junction: St John's Hill Entrance, London

Reconfiguration of St Johns Hill Entrance for Network Rail

The St John’s Hill entrance to Clapham Junction Station, one of the busiest transport hubs in Europe, had become very congested. The pedestrian flow of passengers through the platform subway was being badly restricted by the gateline position and limited circulation space. Robinson Kenning & Gallagher were employed by South West Trains (SSWT) to redesign the area to enable better circulation and passenger movement whilst increasing ticket facilities.

The design solution reduced ‘back of house’ space of the existing ticket office to enable an increase in front of house circulation and ticketing facilities. A new gateline position with increased numbers of gates (including automatic wide-aisle gates) was installed and existing tenancies were relocated and refurbished.

Project Value: £1.5m

View fullsize Clapham main ent_01.JPG
View fullsize Clapham main ent_02.JPG
View fullsize Clapham main ent_04.JPG
View fullsize IMG_0512a.jpg

OTHER TRANSPORT CASE STUDIES:

Featured
Norwich Station, Trainshed Roof
Norwich Station, Trainshed Roof
Stoke MDU, Stoke
Stoke MDU, Stoke
Bury St. Edmunds Station, Suffolk
Bury St. Edmunds Station, Suffolk
Amersham Station, London
Amersham Station, London
Harrow-on-the-Hill, London
Harrow-on-the-Hill, London
Dartford Station, Kent
Dartford Station, Kent
Earlsfield Station, London
Earlsfield Station, London
Basingstoke Station, Hampshire
Basingstoke Station, Hampshire
Euston Station, London
Euston Station, London
Cycle Hubs, South West England
Cycle Hubs, South West England
London Bridge: Maintenance Facility, London
London Bridge: Maintenance Facility, London
Clapham Junction Station: Brighton Yard, London
Clapham Junction Station: Brighton Yard, London
Southampton Station, Hampshire
Southampton Station, Hampshire
Kensal Rise and South Tottenham Overground Stations, London
Kensal Rise and South Tottenham Overground Stations, London
Paddington Station: Waiting Room, London
Paddington Station: Waiting Room, London
Clapham Junction: St John's Hill Entrance, London
Clapham Junction: St John's Hill Entrance, London
Charing Cross Station, London
Charing Cross Station, London
Clapham Junction: Platform 9/10, London
Clapham Junction: Platform 9/10, London
Worcester Park and New Malden Stations, South London
Worcester Park and New Malden Stations, South London
Ilford Station: Public Toilets & Waiting Room, London
Ilford Station: Public Toilets & Waiting Room, London
Kings Cross Station: Roof, London
Kings Cross Station: Roof, London
Victoria Station: Eastern Barrel Roofs, London
Victoria Station: Eastern Barrel Roofs, London
Blackhorse Road Station, London
Blackhorse Road Station, London
categories: Transport
Monday 08.05.19
Posted by Kevin Stocker
 

Charing Cross Station, London

Decongestion Scheme via Multi Asset Framework Agreement (MAFA) for Network Rail

Due to space constraints Charing Cross Station concourse had become highly congested. As a result passenger circulation had become severely hindered, especially during peak periods. Network Rail commissioned VolkerFitzpatrick (Principal Contractor) to produce a viable scheme to reduce Station congestion. Works Included:

  • Demolition of the existing Island retail building on the concourse.

  • Adaptation of the existing ticket barrier line to provide additional ticket gates and improve passenger flow.

  • Rationalisation of the existing concourse furniture such as ticket vending machines and seating.

  • Rationalisation/upgrading of the way-finding signage within the concourse.

  • A listed building application technical support report was prepared by RKG and submitted by Network Rail. 

Project Value: £4.2m

View fullsize IMG_0345.jpg
View fullsize IMG_0343.jpg
View fullsize 3434-Charing-Cross-Concourse-Proposed-01.jpg
View fullsize Charing-Cross---View-One-JPEG-SMALL.jpg
View fullsize charing-x-concourse_historic-&-modern-01a.jpg
View fullsize IMG_0320.jpg
View fullsize IMG_0321.jpg
View fullsize IMG_0310.jpg
View fullsize PA080211.jpg
View fullsize PICT0271.jpg

OTHER TRANSPORT CASE STUDIES:

Featured
Norwich Station, Trainshed Roof
Norwich Station, Trainshed Roof
Stoke MDU, Stoke
Stoke MDU, Stoke
Bury St. Edmunds Station, Suffolk
Bury St. Edmunds Station, Suffolk
Amersham Station, London
Amersham Station, London
Harrow-on-the-Hill, London
Harrow-on-the-Hill, London
Dartford Station, Kent
Dartford Station, Kent
Earlsfield Station, London
Earlsfield Station, London
Basingstoke Station, Hampshire
Basingstoke Station, Hampshire
Euston Station, London
Euston Station, London
Cycle Hubs, South West England
Cycle Hubs, South West England
London Bridge: Maintenance Facility, London
London Bridge: Maintenance Facility, London
Clapham Junction Station: Brighton Yard, London
Clapham Junction Station: Brighton Yard, London
Southampton Station, Hampshire
Southampton Station, Hampshire
Kensal Rise and South Tottenham Overground Stations, London
Kensal Rise and South Tottenham Overground Stations, London
Paddington Station: Waiting Room, London
Paddington Station: Waiting Room, London
Clapham Junction: St John's Hill Entrance, London
Clapham Junction: St John's Hill Entrance, London
Charing Cross Station, London
Charing Cross Station, London
Clapham Junction: Platform 9/10, London
Clapham Junction: Platform 9/10, London
Worcester Park and New Malden Stations, South London
Worcester Park and New Malden Stations, South London
Ilford Station: Public Toilets & Waiting Room, London
Ilford Station: Public Toilets & Waiting Room, London
Kings Cross Station: Roof, London
Kings Cross Station: Roof, London
Victoria Station: Eastern Barrel Roofs, London
Victoria Station: Eastern Barrel Roofs, London
Blackhorse Road Station, London
Blackhorse Road Station, London
categories: Transport
Sunday 08.04.19
Posted by Kevin Stocker
 

Clapham Junction: Platform 9/10, London

Platform 9/10, Waiting Room and Tenancy for Network Rail

The project scope of works included: Alteration and refurbishment of office accommodation areas including the original Station control point, staff facilities and areas used by Revenue Protection to form a new passenger waiting room and retail unit. Additionally, an existing store building was adapted and refurbished to provide new staff accommodation.

The buildings to platforms 9/10 originally comprised a former traction sub-Station and office accommodation used by the Station Manager (and associated support staff), rooms containing comms equipment, a Station control point, staff accommodation facilities and areas used by Revenue Protection. The buildings had many original features and the intention of the design was to retain the original character and styling of the buildings whilst providing new facilities for the staff and passengers.

View fullsize 2012_03_01_220.jpg
View fullsize 2012_03_01_223.jpg

OTHER TRANSPORT CASE STUDIES:

Featured
Norwich Station, Trainshed Roof
Norwich Station, Trainshed Roof
Stoke MDU, Stoke
Stoke MDU, Stoke
Bury St. Edmunds Station, Suffolk
Bury St. Edmunds Station, Suffolk
Amersham Station, London
Amersham Station, London
Harrow-on-the-Hill, London
Harrow-on-the-Hill, London
Dartford Station, Kent
Dartford Station, Kent
Earlsfield Station, London
Earlsfield Station, London
Basingstoke Station, Hampshire
Basingstoke Station, Hampshire
Euston Station, London
Euston Station, London
Cycle Hubs, South West England
Cycle Hubs, South West England
London Bridge: Maintenance Facility, London
London Bridge: Maintenance Facility, London
Clapham Junction Station: Brighton Yard, London
Clapham Junction Station: Brighton Yard, London
Southampton Station, Hampshire
Southampton Station, Hampshire
Kensal Rise and South Tottenham Overground Stations, London
Kensal Rise and South Tottenham Overground Stations, London
Paddington Station: Waiting Room, London
Paddington Station: Waiting Room, London
Clapham Junction: St John's Hill Entrance, London
Clapham Junction: St John's Hill Entrance, London
Charing Cross Station, London
Charing Cross Station, London
Clapham Junction: Platform 9/10, London
Clapham Junction: Platform 9/10, London
Worcester Park and New Malden Stations, South London
Worcester Park and New Malden Stations, South London
Ilford Station: Public Toilets & Waiting Room, London
Ilford Station: Public Toilets & Waiting Room, London
Kings Cross Station: Roof, London
Kings Cross Station: Roof, London
Victoria Station: Eastern Barrel Roofs, London
Victoria Station: Eastern Barrel Roofs, London
Blackhorse Road Station, London
Blackhorse Road Station, London
categories: Transport
Saturday 08.03.19
Posted by Kevin Stocker
 

Worcester Park and New Malden Stations, South London

Morgan Sindall were appointed Principal Contractor for the proposed Access for All works at the stations. Robinson Kenning & Gallagher were appointed as Architects for the scheme.

Read more

categories: Transport, Access for All
Saturday 08.03.19
Posted by 3B Digital
 

Ilford Station: Public Toilets & Waiting Room, London

Robinson Kenning & Gallagher were appointed as Architects for the scheme to provide detailed design for the new lifts and walkways.

Read more

categories: Transport
Saturday 08.03.19
Posted by 3B Digital
 
Newer / Older